Meadowbank and Fountainbridge partners quit 1,169-home schemes
Edinburgh council will look for new suppliers for two flagship brownfield housing schemes after talks over costs and risk broke down.

The City of Edinburgh Council has ended its development partnerships on two of its largest council-led housing schemes, at Meadowbank and Fountainbridge, which together were planned to deliver 1,169 homes.
A report to the council’s finance and resources committee on 17 November said both projects will now go ahead with alternative suppliers after talks over costs and risk broke down. The Meadowbank housing scheme of 705 homes around the rebuilt sports centre had been led by Edinburgh Meadowbank Group (EDMB), a consortium of Graham, Miller Homes and Panacea Property Development.
Meadowbank housing partnership ends over costs
EDMB won a £1.045m pre-development contract for Meadowbank in March 2022 after a competitive procurement. The council’s aim was one of the city’s greenest neighbourhoods, with low-car, low-carbon infrastructure and energy-efficient homes on the 7.1-hectare brownfield site beside the East Coast Main Line. The planned mix was 14 studios, 216 one-bedroom, 337 two-bedroom and 138 three-bedroom homes, 27 of them wheelchair accessible.
The committee report said the Meadowbank housing development had suffered significant delays because the council and the contractor could not agree costs. “In line with contractual arrangements, the agreement has been terminated and the development will progress with an alternative supplier,” it said. The council has said it is now working with one of its framework contractors to build the affordable homes as a first stage of the development.
Fountainbridge and Leamington Square
At Fountainbridge, Cruden Homes (East) and Buccleuch Property were chosen in May 2021 to regenerate the former brewery site on the Union Canal. The scheme, known as Leamington Square, won planning approval for 464 mixed-tenure homes and 30,000 sq ft of mixed-use space, with the council to own 115 homes for social rent and 71 for mid-market rent.
Council officers reported in September that standard terms had not been agreed with the contractor on how risk would be shared and that it had withdrawn from the development agreement. The latest report says the council expects to take the scheme forward with another supplier.
The two sites sit within a busy housing pipeline in the city. Work started last month on 847 homes at Granton Waterfront, while The Social Hub has submitted £200m plans for the neighbouring Fountain Brewery site in Fountainbridge.
Read more Edinburgh business news
Sources: City of Edinburgh Council, Meadowbank New Build Housing Development integrated impact assessment